Village of Breckenridge - Water Project Notes / Info Log

Date Notes / Updates
5/11/2010 Prep work started for installing Taps
5-12-2010 Tap @ Fourth & Oak Alley Complete
5-14-2010 Tap @ 7th & Birch Complete - Fourth / Chestnut, 8th & Chestnut Taps Not Completed
5-17 & 18 Taps worked on at 6th and Cedar & Completed and Started on Cedar and 8th Street.
5-26-2010 Completed taps at 2nd and Birch and 3rd and Birch - Working on M46 towards the new tower
5-27 & 28-2010 Completed Tap/s on 2nd & Oak and 3rd & Oak (Downtown areas)
5-28-2010 Working on Tap at Eastman & Sexton Streets (Completed)
6-1-2010  Back to 8th and Chestnut. (Completed)
6-1-7-2010 Completed Taps at 4th and Birch,
6-8-2010 Finished Tap at M46 & 8th
6-14-2010 Late Change, Completed a Tap at First and Birch
6-16-2010 Tap at Summit@Maple, Summit@Eaton and Maple@Main
6-17-2010 Birch@8th
6-18-2010 Milled Sexton, Maple, Eaton
7-15-2010 Update, Taps are complete and many locations are seeing streets milled, new water lines installed, pressure tested and activated upon approved test results.
8-25-2010 New lines continue to be installed with many already complete, Several roads on the north side of town are now complete with new pavement, while others are being prepped.
Cedar 8” water main install
Wisner 12” water main install
Start foundation for water tower
Start paving on Eaton St.
Late Sept North Side of Breckenridge is done and most of the south side have had all the lines and taps done with just some road work to finish
Mid Nov South side has had many sidewalks repaired, roads completed with the project now centered on the water tower
Mid Dec Water tower is built and all but done, painting to be done later.
12-13 New pump to be purchased for the water treatment plant